Jobs In 2008

Project

Customer

Year 2009

Completed

Fabricate And Erect 39 Nos Building

Rainbow
Construction Limited

15th March 2007

Still In Progress

Trinidad Gtl Plant Control Room / Office At Pointe A- Pierre

Ventech Engineering Services Inc.

2th July 2007

Still In Progress

Foundation For Gtl  Plant

Ventech Engineering Services Inc.

2th July 2007

Still In Progress

Steel Fabrication And Erection Blue Waters- Warehouse  Of Structur
E 860 Ft Long X 200 Ft Wide

Lone Star Construction Limited

3rd March 2008

Still In Progress

Mains Repairs & Installation of Stop Cocks, Curb Valves And Materials On As An And When Required Basis

Water And Sewerage Authority

2008

Still In Progress

Cement Mill # 3 Proposed Access Platform To Mill Inlet

Trinidad Cement Limited

1st January 2009

Still In Progress

Safety Platform At Motor And Gearbox 8-12 Reject Pan Conveyor At Kiln # 4

Trinidad Cement Limited

11th March 2009

Still In Progress

Building ‘T’ Building Construction Technology Workshop

Cbe Trinidad Limited

31st March 2009

Still In Progress

To Construct Foundation For J466c Pump And Associated Piping Supplort

Industrial Plant Services Limited

4th April 2009

Still In Progress

 

Repairs To Kiln # 4 Reject Pan Conveyor Hopper East Side

Trinidad Cement Limited

2nd April 2009

3rd April 2009

Repairs To Kiln # 4 Reject Chute

Trinidad Cement Limited

31st March 2009

3rd April 2009

Safety Platform At Motor & Gearbox 8.12 Reject Pan Conveyor At Kiln # 4

Trinidad Cement Limited

12th March 2009

3rd April 2009